How Many Bags of Mortar Do You Need for Your Brick or Block Wall?

Calculate the exact number of 80 lb or 60 lb mortar mix bags needed for brick and CMU block walls, including joint size adjustments, waste allowance, and material cost.

Mortar Calculator
= 675 bricks at 6.75/sq ft
Pricing (edit to match local rates)
Bricks
675
From 100 sq ft wall area
Recommended Buy
80 lb Bags
62 bags · $372.00
Purchase OptionQuantityEst. Cost
80 lb BagsBest value62 bags$372.00
60 lb Bags83 bags$415.00
Best value: 80 lb Bags at $372.0080 lb bags are more cost-effective per pound of mortar. They are heavier to handle but give you the best material value.
Consider buying by the palletFor large jobs requiring 30+ bags, most suppliers offer pallet pricing (typically 35-42 bags per pallet) at a significant discount. Ask your supplier about bulk rates.
This is an estimate based on standard mortar joint sizes and typical coverage rates. Actual mortar usage varies with joint profile, tooling, mix consistency, and mason technique. Always buy extra to avoid running short mid-job.

Essential Equipment and Materials for Masonry Work

Estimating mortar requirements accurately is only half the battle. Before laying your first course of brick or block, organize your tools, materials, and safety equipment to maintain a continuous workflow and prevent the mortar from stiffening on the mixing board.

  • Essential Tools: London or Philadelphia pattern masonry trowel, margin trowel, concave jointer or tuck pointer, mortar board (hawk or plywood sheet), 5-gallon buckets, mortar mixer or heavy-duty mixing tub, hoe with cutouts, line pins and mason line, and a 4-foot spirit level.
  • Core Materials: Pre-mixed mortar bags (Type N or Type S), clean potable water, masonry ties or wall anchors, and brick or concrete masonry units (CMU).
  • Safety Equipment: N95 dust mask or respirator (silica dust protection during dry mixing), heavy-duty rubber work gloves (alkaline mortar protection), safety glasses with side shields, and thick knee pads.
  • Nice-to-Have Additions: Masonry sponge, plastic sheeting (to keep work moist or protect against sudden rain), mortar color pigments, and an acid-free masonry cleaner for final washdown.

Mortar Mix Types and Bag Coverage Reference Guide

Mortar selection depends on whether you are building above grade, below grade, or restoring historical brickwork. Pre-mixed mortar bags typically come in 80 lb and 60 lb options. Standard coverage relies on a standard 3/8-inch bed and head joint.

Mortar mix classifications, compressive strengths, and practical bag yields.
Mortar TypeCompressive StrengthPrimary Application80 lb Bag YieldApprox. Coverage
Type N (80 lb)750 psiExterior above-grade walls, brick veneer, chimneys0.67 cu ft130–140 standard bricks
Type N (60 lb)750 psiSmall repairs, short garden walls, brick veneer0.50 cu ft95–105 standard bricks
Type S (80 lb)1,800 psiBelow-grade foundation walls, CMU blocks, retaining walls0.67 cu ft30–34 standard 8x8x16 CMUs
Type S (60 lb)1,800 psiLight concrete block work, structural repairs0.50 cu ft22–25 standard 8x8x16 CMUs
Type M (80 lb)2,500 psiHeavy load-bearing walls, stone masonry, footings0.67 cu ft120–130 standard bricks
Type O (80 lb)350 psiHistoric restoration, soft natural stone, interior veneer0.67 cu ft130–140 standard bricks

Frequent Masonry Mortar Estimation Errors

Ignoring Mortar Waste and Droppage: Masons experience material loss as mortar falls off boards, extrudes out of joints during striking, or hardens in the pan before application. Estimating exact theoretical quantities without adding a 10% to 15% waste allowance almost always leaves you short before completing the top course.

Confusing Mortar Joint Width and Depth: Standard estimates rely on a 3/8-inch joint. Increasing joint width to 1/2 inch or using deeper recessed joint profiles increases total mortar volume requirements by over 30%. Failing to adjust material estimates for wider joints causes significant material shortfalls.

Assuming Concrete Bags and Mortar Bags Are Interchangeable: Concrete mix contains coarse stone aggregate designed for structural pours, whereas mortar contains fine sand, cement, and hydrated lime tailored for thin joint bonding. Purchasing concrete mix for unit masonry leads to improper bonding and clogged joints. If you need structural footings under your wall, use a dedicated concrete bag calculator rather than mortar calculations.

Underestimating Block Web Bedding: On concrete block walls, inexperienced masons sometimes assume full-bed mortar coverage across the entire block surface. CMUs are typically laid with face-shell bedding, where mortar is applied only to the outer edges. Miscalculating this area leads to ordering double the required mortar mix.

Neglecting Absorption Rates of Dry Units: High-suction clay bricks draw moisture rapidly out of fresh mortar. Masons must wet porous units or adjust batch sizing, as dry bricks lead to retempering or discarded mortar that has lost workability.

Calculating Mortar Volume and Bag Quantities

Estimating mortar requires knowing the surface area of your wall, the density of units per square foot, joint thickness, and expected waste. Standard modular bricks (3-5/8 inches wide by 2-1/4 inches high by 7-5/8 inches long) require approximately 6.75 bricks per square foot when laid with 3/8-inch joints. Concrete masonry units (8x8x16 nominal CMU) require 1.125 blocks per square foot.

Mathematical Formulas for Mortar Estimation

Use these formulas to calculate exact material quantities for brick or CMU block projects:

  • Brick Count = Wall Area (sq ft) × 6.75 × (1 + Waste Factor)
  • 80 lb Mortar Bags (Brick) = Total Brick Count ÷ 135
  • CMU Block Count = Wall Area (sq ft) × 1.125 × (1 + Waste Factor)
  • 80 lb Mortar Bags (CMU) = Total CMU Block Count ÷ 32
  • 60 lb Mortar Bags = 80 lb Bag Requirement ÷ 0.75

Step-by-Step Practical Calculation Example

Suppose you plan to construct a 12-foot wide by 10-foot tall brick veneer wall using standard modular bricks and 80 lb pre-mixed Type N mortar bags with a 10% waste factor.

Step 1: Calculate Total Wall Area.

12 ft × 10 ft = 120 sq ft of wall surface.

Step 2: Calculate Brick Requirement.

Base bricks = 120 sq ft × 6.75 = 810 bricks. Adding 10% waste (810 × 1.10) equals 891 bricks. You can confirm block or unit dimensions using our brick calculator.

Step 3: Calculate Mortar Bag Requirement.

Divide the total brick count by the coverage rate per 80 lb bag (135 bricks per bag):

891 ÷ 135 = 6.6 bags.

Always round up to the nearest full bag. You will need 7 bags of 80 lb Type N mortar mix. If buying 60 lb bags, divide 6.6 by 0.75 = 8.8 bags, which rounds up to 9 bags of 60 lb mortar mix.

If you were building this wall out of standard 8x8x16 blocks instead, 120 sq ft × 1.125 × 1.10 waste = 149 blocks. Dividing 149 by 32 blocks per bag yields 4.65, so you would purchase 5 bags of 80 lb Type S mortar mix. Use our concrete block calculator to verify block requirements for larger or more complex foundations.

Pre-Mixed Mortar Bags vs. Jobsite Sand and Cement Mixes

When planning a masonry project, you can choose between buying factory pre-blended bagged mortar mix or site-mixing individual raw materials (Portland cement, hydrated lime, and masonry sand).

Pre-Mixed Bags (Type N or S): Pre-bagged mix contains factory-proportioned cement, lime, and graded sand. You simply add clean water. This option eliminates proportioning errors, ensures batch-to-batch color consistency, and is ideal for DIYers and small-to-medium commercial jobs. The trade-off is a higher per-cubic-foot material cost compared to buying sand in bulk.

Site-Mixed Scratch Mortar: Mixing raw materials requires buying bags of Portland cement, bags of hydrated lime, and loose tons of masonry sand. Standard Type N mortar ratio is 1 part Portland cement, 1 part lime, and 6 parts loose damp sand (1:1:6). This approach drastically lowers unit material costs on large projects involving thousands of bricks. However, it demands consistent volume measuring on site, strict moisture management of sand piles, and increased labor overhead.

  • Pro Tip: For projects requiring fewer than 20 to 25 bags of mortar (around 2,500 bricks or 600 blocks), use pre-mixed 80 lb bags. The consistency, saved setup time, and eliminated sand pile waste easily outweigh the small price premium.

Frequently Asked Questions

How many standard bricks can I lay with one 80 lb bag of mortar mix?

One 80 lb bag of standard pre-mixed mortar (Type N or Type S) yields about 0.67 cubic feet of wet mortar, which is enough to lay roughly 130 to 140 standard modular bricks with standard 3/8-inch bed and head joints.

How many concrete blocks (CMU) can one bag of mortar cover?

An 80 lb bag of mortar mix will lay approximately 30 to 34 standard 8x8x16 concrete masonry units (CMUs) using face-shell bedding and 3/8-inch mortar joints. A 60 lb bag covers roughly 22 to 25 blocks.

What is the primary difference between Type N and Type S mortar mix?

Type N mortar offers moderate compressive strength (around 750 psi) and high workability, making it ideal for above-grade exterior walls, chimneys, and brick veneers. Type S provides higher compressive strength (1,800 psi) and stronger lateral bond strength, making it mandatory for below-grade foundation walls, retaining walls, and structural CMU block work.

How much water do I add to an 80 lb bag of pre-mixed mortar?

Most standard 80 lb bags of mortar require approximately 4 to 5 quarts (1.0 to 1.25 gallons) of clean water. Add water gradually while mixing until you achieve a smooth, buttery consistency that holds its shape on a trowel without slumping.

How does increasing mortar joint thickness affect bag quantities?

Increasing joint thickness from the standard 3/8-inch to 1/2-inch increases mortar volume requirements by roughly 30% to 35%. If your project uses 1/2-inch joints, multiply your baseline calculated bag requirement by 1.33.

How long does mixed mortar remain usable on the mortar board?

Under standard outdoor temperatures (around 70°F), mixed mortar remains usable for 1.5 to 2 hours. In hot, windy conditions, mortar loses moisture rapidly and may dry out in 30 to 45 minutes. You can retemper mortar by adding a small amount of water during the first 1.5 hours, but discard any mortar older than 2 hours as cement hydration begins.